Public Utility Sewer Connections

Public Utility Sewer Connections

Approved United Utilities contractor

Connecting to the public sewer system can be costly and time consuming but, as a United Utilities approved contractor, we’re here to help from start to finish. 

Our team has undertaken a variety of water sewer connections, installation of rising mains, outfalls and sewer diversions.

How long will it take?
Time to get a Section 106 license to connect to a public sewer 3-6 weeks.
Time needed to get a Section 50 license to dig up the road 3-10 weeks.
Notice period to use a Section 50 licence 1-12 weeks.
Time taken to do the work 3-10 days approx

Don’t leave it to chance, contact us today

Whether you’re planning a single home or a more complex project needing major infrastructure you can never start the planning application to connect to the public sewer system too early. 

Our groundworks team are fully trained to work in confined spaces as well as in operating all machinery needed to complete the job to our high standards. 